Short answer
Do a cavity shaft wall takeoff by its parts: shaftliner area is linear feet times height, with one 2 ft panel per 2 ft of wall; C-H studs are the run length divided by 2 ft, plus one; J-runner goes at the floor, the top and each end. Add the room-side layers from the UL design.
A shaft wall takeoff counts shaftliner, C-H studs and J-track, not just board, because a shaft wall is built from one side: it encloses an elevator, stair or duct shaft, and the other side is open. That changes everything a normal partition takeoff assumes. The studs are a different shape, the board on the shaft side is 1 in. shaftliner set between the studs, and the track is J-shaped. This guide walks through a cavity shaft wall takeoff piece by piece.
What is a shaft wall?
A shaft wall is a fire-rated gypsum wall built entirely from outside a shaft, using 1 in. shaftliner panels held in C-H or similar studs, with finish layers on the room side only. It is used where the inside of the shaft cannot be reached to hang board.
01Know the parts of the system
A cavity shaft wall system is sold as a set of matched parts by the board and stud manufacturers. Your takeoff needs a line for each:
- Shaftliner panels: 1 in. gypsum panels with a fire-resistant core, usually 2 ft wide, cut to the wall height and slid between the studs on the shaft side.
- C-H studs (or C-T or I-studs, by manufacturer): studs shaped to grip the liner panels' edges, set 2 ft on center, one between every pair of panels.
- J-runners (J-track): track with one long leg, at the floor, at the top and at each vertical end where the wall meets other construction.
- Room-side board: the face layers on the corridor or room side, by the UL design, often 5/8 in. Type X or a Type C board.
A cavity shaft wall is always a rated assembly, so start from its UL design number, the same way you would for any rated wall.
02Measure the shaftliner
Shaftliner is one layer on the shaft side:
shaftliner area = linear feet × height
Count panels as well as area, because panels are cut to height and set one per 2 ft of wall. For each wall run, the panel count is the run length divided by 2 ft, rounded up. Check the lengths your supplier stocks: when the shaft is taller than the longest panel, the panels are stacked and the manufacturer's detail sets how the joints are made, which adds cuts and labor.
03Count C-H studs, J-runners and openings
Studs and runners are counted, not estimated from area:
| Part | How to count it | Unit |
|---|---|---|
| C-H studs | Run length ÷ 2 ft, plus 1, per run, each at full height | Each, by length |
| J-runner, floor and top | Run length, top and bottom | Linear feet |
| J-runner, vertical | Height at each end of a run and at each side of an opening | Linear feet |
| Opening framing | Per the manufacturer's door and duct opening details | Each opening |
Stud depth and gauge come from the manufacturer's limiting-height tables, not from habit. Elevator shafts see air pressure from the moving car, so the design pressure on the drawings or in the specifications decides which stud reaches the height. Elevator door openings usually need heavier jamb framing, and each one is a line of its own.
04Count the room-side layers by the design
The room side is measured like any rated wall:
room-side board area = linear feet × height × layers on the room side
Keep each board type on its own line. If the design calls for Type C, Type X cannot be swapped in. The shaft side gets no finish; the room side is finished to the level the specifications set.
05Price the labor for one-sided work
Shaft walls go up from the floor outside the shaft, often before the elevator contractor is in, and panels are handled at an open shaft edge. Allow for fall protection and stocking at each floor, and price shaft walls on their own labor line. A production rate taken from ordinary partitions will be wrong in both directions: fewer layers to hang on the shaft side, more cutting and handling at every panel.
Worked example: a four-stop elevator shaft
A two-hour elevator shaft runs four floors, 12 ft floor to floor, 48 ft in all. Three sides are shaft wall, 8 ft + 8 ft + 7 ft = 23 LF; the fourth side is concrete. The design, as an example, is 1 in. shaftliner with two layers of 5/8 in. Type X on the room side, 4 in. C-H studs. The takeoff goes floor by floor, 12 ft high, because panels and studs are set one floor at a time.
| Line | Per floor | Four floors |
|---|---|---|
| Shaftliner (sq ft) | 23 LF × 12 ft = 276 | 1,104 |
| Shaftliner panels, 2 ft wide | 4 + 4 + 4 = 12 | 48 |
| C-H studs, 12 ft | 5 + 5 + 5 = 15 | 60 |
| J-runner, floor and top (LF) | 46 | 184 |
| J-runner, vertical at ends (LF) | 2 ends × 12 ft = 24 | 96 |
| Room-side Type X, 2 layers (sq ft) | 23 × 12 × 2 = 552 | 2,208 |
| Elevator door openings | 1 | 4 |
The 7 ft run takes four panels because 7 ÷ 2 rounds up to 4, with one panel ripped to fit. Count the room-side board in sheets per wall, the same way as any rated wall, then add waste on it and on the shaftliner offcuts, by your own job history.
Common mistakes on shaft walls
- Pricing it as a normal partition. A shaft wall has its own parts, its own design number and one-sided labor.
- Counting shaftliner by area only. Panels go in one per 2 ft and are cut to height; count them per run, and check stock lengths for tall shafts.
- Picking the stud from habit. Elevator shafts carry air pressure; the stud comes from the manufacturer's limiting-height table at the design pressure.
- Forgetting the openings. Elevator door and duct openings have their own framing details, and each is a line.
- Leaving out the safety and stocking time. Work at an open shaft edge needs fall protection and material at each floor, and that is labor.
Questions estimators ask
- What is a C-H stud?
- A steel stud shaped like a C with an H-shaped web that grips the edges of two shaftliner panels. Set 2 ft on center, one between every pair of panels, it lets the wall be built from outside the shaft. Some manufacturers use C-T or I-studs for the same job.
- How thick is shaftliner?
- Shaftliner panels are 1 in. thick with a fire-resistant core and are usually 2 ft wide. They are cut to the wall height and set on the shaft side, between the studs.
- What is J-track used for in a shaft wall?
- J-runner, or J-track, has one long leg. It holds the shaftliner and studs at the floor, at the top and at each vertical end where the shaft wall meets other construction, and at the sides of openings. Count it in linear feet.
- How do I pick the stud depth for an elevator shaft wall?
- From the manufacturer's limiting-height tables at the design pressure on the drawings or in the specifications. Elevator shafts see air pressure from the moving car, so the stud has to reach the wall height at that pressure.
Sources
- Peterson & Dagostino, Estimating in Building Construction, 9th ed. (Pearson, 2019), §17-3 Types of Assemblies
- Peterson & Dagostino, Estimating in Building Construction, 9th ed. (Pearson, 2019), §17-4 Drywall Types
- Peterson & Dagostino, Estimating in Building Construction, 9th ed. (Pearson, 2019), §17-6 Estimating Drywall
- UL Product iQ: fire-resistance design listings (BXUV)
- Gypsum Association, GA-600 Fire Resistance and Sound Control Design Manual
- ASTM C1396, Standard Specification for Gypsum Board (gypsum shaftliner board)
- Manufacturers' cavity shaft wall system catalogs and limiting-height tables
- ASTM C754, Standard Specification for Installation of Steel Framing Members to Receive Screw-Attached Gypsum Panel Products
- ASTM C840, Standard Specification for Application and Finishing of Gypsum Board