Short answer
GCs level drywall bids by checking each one for scope, addenda, tax and conformance, then putting them side by side on a leveling sheet, one row per scope item. Every exclusion gets a plug, the cost to buy it elsewhere, so all bids cover the same work. The leveled totals are tested against cost history before award.
Bid leveling is how a general contractor turns three drywall bids that each cover something different into three prices that cover the same work. The low number on bid day is not always the low bid after leveling. This guide walks through how GCs level drywall subcontractor bids, from the GC's side, so a drywall sub can see exactly what gets added to their number and why.
What is bid leveling?
Bid leveling is adjusting several subcontractor bids so they cover the same scope, by adding the cost of anything one bidder excluded and taking out anything extra, so the prices can be compared directly. The tool is a leveling sheet: one column per bidder, one row per scope item.
01Check each bid for completeness first
Before comparing prices, the GC's estimator checks every bid on its own. The questions are the same on every job:
- Does it cover the whole scope of work in the bid package?
- Does it acknowledge every addendum by number?
- Are freight and sales tax included, or excluded?
- Does it conform to the drawings and specifications, or does it price a substitute?
- Are the exclusions listed, and are any of them items the GC must now buy elsewhere?
If something is missing or unclear, the GC calls the sub and asks. A good GC writes the clarification down, so the answer is part of the bid when the subcontract is written.
02Build the leveling sheet
The leveling sheet has one column per bidder and one row per scope item from the bid package. Every row is marked included, excluded or not mentioned. A typical drywall leveling sheet has rows for:
- Framing, board and finish by partition type
- Rated assemblies and head-of-wall joints
- Finish levels, room by room
- Blocking and backing, access panel and frame installation
- Firestopping, hoisting and stocking, lifts, cleanup and temporary protection
- Alternates and unit prices, kept separate from the base bid
03Plug every gap with a number
Wherever a bidder excludes or skips an item that another bidder carries, the GC adds a plug: the cost to buy that item elsewhere or to self-perform it. Plugs come from another bidder's breakout, from the GC's own takeoff or from cost history. An alternate a bidder folded into their base is taken back out.
After plugging, every column covers the same scope, and the totals can be compared directly.
04Test the leveled numbers against history
A leveled bid can still be too high or too low. The GC compares each one with the cost of the same work on a similar recent job, scaled by a quantity that tracks the cost, such as square feet of floor or square feet of board. A bid far below that range is a risk, not a bargain: a sub who is losing money on the job tends to push change orders, slow down or cut corners, and the GC pays for that later.
05Pick the best bid, not only the lowest
Price usually decides, but not alone. GCs also weigh whether the sub can staff the job, meet the schedule and the quality standard, and how they performed last time. A trusted sub a little above the low bid often wins, because a missed schedule costs the GC more than the difference.
What this means for your bid
- Write your scope in the order of the GC's bid package, so each line maps to a leveling row.
- Acknowledge every addendum by number.
- List exclusions plainly. A hidden exclusion becomes a plug at the GC's price, not yours.
- Put alternates and unit prices on their own lines.
- If you are far below the other bids, expect a call, and check your takeoff before you answer.
Worked example: three drywall bids on an office TI
Three drywall subs bid a 40,000 sq ft office fit-out. The numbers are an example.
| Line | Sub A | Sub B | Sub C |
|---|---|---|---|
| Base bid as submitted | $412,000 | $368,000 | $395,000 |
| Alternate folded into base, removed | −$12,000 | ||
| Head-of-wall firestopping, excluded | +$14,500 | ||
| Level 5 at lobby, excluded | +$6,200 | ||
| Hoisting and stocking, excluded | +$9,000 | ||
| Patch-back after other trades, excluded | +$4,800 | ||
| Leveled total | $400,000 | $397,700 | $399,800 |
Sub B was $44,000 low on bid day and is $2,300 low after leveling. At a recent similar job's $9.80 per sq ft of floor, the expected cost is about $392,000, so all three leveled bids are in range, and the award now turns on schedule, staffing and past performance.
Common mistakes that cost subs at leveling
- An unacknowledged addendum. A GC can set a bid aside for it even when the addendum changes nothing you price.
- Exclusions buried in the fine print. They are found anyway, and plugged at the GC's number.
- An alternate folded into the base. It makes the base look high and gets taken back out.
- A scope in a different order from the bid package. Rows the GC cannot match get marked "not mentioned".
- Clarifications by phone only. If the answer is not in writing, it is not in the subcontract.
Questions estimators ask
- What does a GC check first in a drywall bid?
- That it covers the whole scope in the bid package, acknowledges every addendum by number, states whether tax and freight are in, conforms to the drawings and specifications, and lists its exclusions. Missing answers get a call, then a plug.
- What is a plug number in bid leveling?
- A plug is the amount a GC adds to a bid for an item the bidder excluded or skipped. It comes from another bidder's breakout, the GC's own takeoff or cost history, and it is usually at the GC's price, not the sub's.
- Does the lowest drywall bid always win?
- No. After leveling, the low bid on bid day may not be low any more, and GCs also weigh staffing, schedule, quality and past performance. A bid far below the others or below cost history is treated as a risk.
- How can a drywall sub make their bid easier to level?
- Follow the order of the GC's bid package, acknowledge every addendum by number, list exclusions plainly and keep alternates and unit prices on their own lines.
Sources
- Peterson & Dagostino, Estimating in Building Construction, 9th ed. (Pearson, 2019), §9-4 Checking Specialty Contractor Bids
- Peterson & Dagostino, Estimating in Building Construction, 9th ed. (Pearson, 2019), §9-5 Selecting Specialty Contractors